Board Approves Design Development Submittal For UHS Fitness Center And Elementary School #1
On Monday, October 8, 2018, the Urbandale CSD School Board approved the Design Development Submittal for the UHS Fitness Center and Elementary School #1 on the Olmsted site. What this means is that at this point, approximately 90% of the decisions regarding design development have been made and DLR Group, Stahl Construction, and Urbandale CSD will now proceed to the Construction Documentation Phase. Check out the most recent images below for both projects!
Upcoming milestones for both projects include:
Elementary School #1 (Olmsted site)
- December 10, 2018 School Board establishes Bid Date
- January 10, 2019 Contract Documents issued for bidding
- February 7, 2019 Bids Received
- February 25, 2019 School Board reviews bids for possible award
Urbandale High School Fitness Center
- December 10, 2018 School Board establishes Bid Date
- December 13, 2018 Contract Documents issued for bidding
- January 15, 2019 Bids Received
- January 28, 2019 School Board reviews bids for possible award