April 2020 Design and Construction Update
District Administration is working closely with our design team (DLR Group) and contractors (Stahl for Olmsted Elementary School; Rochon Corporation for UHS Fitness Center, UHS/Webster main entry, and Webster computer lab; Two Rivers Group for UHS HVAC). Below you’ll find an updated summary of actions that have been taking place for multiple construction projects.
PROJECT UPDATES
UHS Fitness Center
- Check out renderings of the UHS Fitness Center!
- Included below are progress photos of the fitness center exterior and interior main lobby area/restrooms as of 3/26/20. Anticipated completion timeframe is spring 2020.
- Part 1: Fitness Center / Multi-Purpose Room Construction
- Brickwork is done.
- Interior block is complete.
- Square duct and round duct is installed; spiro duct has been installed.
- Window work is completed
- Awaiting delivery of flooring systems. These are expected in mid April. All other finishes are completed.
- Part 2: Gym Lobby Restrooms
- Completed
- Part 3: Gym Lobby
- Area is a workspace and a construction zone
- Work is completed in this area.
- Part 4: North Gym Hallway Locker Rooms
- Installation of individual shower units have been completed
- Epoxy finishes have been installed on walls and floors
- New restroom partitions have been installed
- Final finish work related to the ceilings will be completed summer 2020
- Part 5: “Trophy Case Hallway”
- Currently available for use. There will be times throughout the Spring when the hallway will be closed due to work being done in the new construction area
- Doorways to the new construction have been cut, awaiting aluminum door installation.
- Patching and painting of walls and bulkheads is completed.
- Part 6: North Gym Balcony Bleachers
- Completed
- Overview of space: The new space will feature an approximate 3,800 sq ft multi-purpose fitness area with flooring to support a host of activities such as yoga, cheer practice, and dance practice. Also featured will be an approximate 9,300 sq ft weight/fitness area that will accommodate free weight training, and speed and agility enhancement with a single lane of track and of turf. Approximately 4,900 sq ft will include circulation areas, lobby, new concessions, and new restrooms that support activities in the two existing gymnasiums. The Fitness Center will support general wellness of all UHS students as the spaces will be incorporated into the daily academic Physical Education (P.E.) program. Spaces may also support Urbandale Community Education Classes.
New Olmsted Elementary
- Design/photos: Olmsted Elementary School
- Included below are progress photos of the new Olmsted Elementary school as 3/26/20.
- Olmsted Elementary is scheduled to open fall 2021 (for the 2021-22 school year).
- Topsoil has been stripped, and stockpiled, and building rough grade
- Groundbreaking Ceremony was held on September 30, 2019
- Update: Naming of the New Elementary School
- Due to high groundwater and soil moisture content, a “Rammed Aggregate Pier” system is being used to stabilize the soil and foundation of the new structure. This requires 770 holes to be bored around the building perimeter, and load bearing interior walls, that are then filled with aggregate to form a solid, durable pier that can then be incorporated into the foundation system. Pier was completed the 2nd week in January.
- Foundations are poured
- Much of the fabricated steel and precast concrete panels are fabricated, and have been shipped and are on site.
- Steel erection has begun at building D. Currently, the full steel “skeleton” has been erected. Bar joist and floor decking are being installed. Roof decking will be installed soon.
- Blockwork is completed at the firewall between buildings C and D.
- Blockwork for the safe room and firewall in area A is in process
- Underground utilities are being installed
- Subgrade preparation for the main parking lot is in process
- Work continues even with very wet conditions
PPEL PROJECT UPDATES
UHS and Webster Elementary Main Entry Renovations; Webster Computer Lab Renovation
An important part of providing a safe and secure environment for all students, staff, and patrons of the Urbandale CSD is consistently evaluating facilities to maintain a balance of a welcoming and secure campus. Following further evaluation, door entry/lobby modifications are being planned at the Urbandale High School Main Entry and the Webster Elementary Main Entry in order to provide immediate and direct access to the Main Office upon arrival at each school building. In addition, we will be removing the tiered floor in the Webster Elementary computer lab in order to make the floor flat so the space can be better utilized.
- Urbandale CSD School Board provided approval of the Design Development
- Urbandale CSD School Board provided approval of Rochon Corporation as our construction partners for these projects.
- Webster computer lab remodel has been completed.
- Demolition of the areas to contain doors to the offices was completed over winter break.
- The stairway at the HS entry has been installed.
- Temporary filler panels have been installed at both Webster and the HS until the doors and frames are delivered after fabrication
- Procurement and delivery of aluminum curtain wall, doors, door hardware, and locking mechanisms are ongoing.
- Additional work on installation of doors, hardware, locks and door entry systems scheduled for March/April. Some re-routing to the gym door from Webster’s main entrance may need to occur to facilitate work at that location.
- Anticipated completion date for the UHS and Webster main entry renovations is summer 2020.
UHS HVAC Renovations
Indoor Air Quality and Environmental Comfort are key to enhancing the learning and working environment of all Urbandale CSD facilities. Over time, building system components age and need more than regular maintenance attention to maintain a healthy and comfortable environment. The oldest remaining portion of the original high school, the north gymnasium area, has HVAC systems that have exceeded their intended life span. Over the course of the 2019-20 school year and the following summer, the District is investing in HVAC upgrades to replace aged equipment, as well as add cooling to these spaces.
- Urbandale CSD School Board provided approval of the Design Development
- Part 1: South Gym
- All existing duct work and mechanical units have been removed and new work on the gym floor level has been completed
- We are back in the gym space at this time
- Remaining work to be completed in the evening
- Part 2: Weight Room
- All existing duct work has been removed and the new duct is installed
- Part 3: Locker Rooms, Training Room, Auxiliary Spaces
- The installation of new duct work is completed in the South gym hallway Electrical work and drop ceiling work is completed
- Sprinkler extensions are completed
- The locker rooms and the training room are operational
- Part 4: Balance of Work
- Welding completed in the Wrestling Room and Fitness Room
- All four of the units for the Gyms are installed on the roof.
- Additional work continues in this area and work will be conducted in the evening hours
- The balance of work to complete the project to include the North Gym and surrounding area and the Wrestling Room has begun; great deal has been completed
- Electrical service for the fitness center and part of the HVAC renovations has been completed.
- Gas service has been installed, and lines to the rooftop units have been installed.
- South Gym is being heated by new rooftop units.
- All old air handling equipment has been demolished
- Boilers in the gym are have been shut down, and demolition of piping systems has begun
- Controls programming has begun