April 2023 Design and Construction Update

District Administration is working closely with our design team (DLR Group) and contractors (Stahl Construction). Below you’ll find an updated summary of actions that have been taking place for Valerius Elementary.

PROJECT UPDATES

Valerius Elementary

  • 90th Street work has started and is continuing
  • Overflow parking has been poured
  • Southeast parking/bus lane has been prepped and is ready for concrete
  • Grading on the east side has started and will continue 
  • Mason is complete
  • Chilled and Hot water supply and return piping is complete, currently circulating water  
  • Area A
    • Ceilings installation is continuing 
    • Flooring is continuing 
    • Final painting is continuing 
    • Casework installation is complete
    • Locker installation id complete
  • Area B
    • Glass, B1 Lobby is complete
    • Overhead MEP rough-in has been completed
    • Painting on 2nd floor has started
    • Learning stairs handrails has started
    • Electrical and duct-work has B2 and commons is completed
    • Painting in commons ceiling has finished
    • 1st Floor electrical rough in is continuing
    • 1st Floor drywall is continuing
    • Commons Clouds have started 
  • Area C
    • Servery Terrazzo is complete
    • Servery ceramic wall tile is complete
    • Kitchen Equipment has started and is ongoing 
    • Kitchen ceiling grid has started
    • Boiler room equipment continuing with connections and hook ups 
    • Boilers started on 4/12
    • Chillers scheduled to start 4/20
    • Gym flooring is complete, sealed and painted
  • Area D
    • Windows are continuing
    • Overhead Inspections are ongoing
    • D2 ceiling grid has started
    • D2 casework is continuing 
    • D1 drywall finishing has started and is continuing 
    • D1 paint has started
    • D1 ceramic tile has started
  • Scheduled to open Fall 2023-24

Valerius Construction Update April 2023